Wednesday evening’s liftoff of SLS and Artemis II from Launch Complex 39B at Kennedy Space Center was the kind of moment the Space Coast was made for.

NASA’s Space Launch System cleared the tower at 6:35 PM. EDT, lighting up the skies over 400,000 visiting spectators and illuminating the region as it sent Commander Reid Wiseman, Pilot Victor Glover, and Mission Specialists Christina Koch and Jeremy Hansen on their way to the Moon.

Every major ascent milestone from Max-Q through core stage separation came off without a visible hitch, and the Orion spacecraft — named Integrity by its crew has been performing nearly flawlessly since reaching orbit.

Upcoming Events

A Brief Communications Glitch After Liftoff

One issue of concern happened not long after liftoff. “About 51 minutes into the flight, during a planned handover between satellites, the Orion spacecraft experienced a communications issue that led to a temporary partial loss of communications,” said NASA Administrator Jared Isaacman in a press briefing after launch. “The uplink from Capcom to the crew was being heard by the crew, but we could not hear their responses. For a brief period of time, there were no issues with the vehicle itself. Communications with the crew have now been restored,” he concluded.

“It happened during a handover. Sometimes ground configuration can get a little squirrely, and you have to get that right. Hopefully that is what it was, but we will chase it down,” said Norm Knight, NASA Director of Flight Operations.


Talk of Titusville will always be free to access.
If you love what we’re doing, please consider becoming a monthly Supporter HERE.

He illuminated the issue further, saying, “They did have intermittent forward and return links, so the commands they needed on board were never an issue. It was just unusual for it to drop out for a couple of minutes, and that is why we are telling you about it.”

Where We Are And Where We Are Going

Flight Day 1 has been a steady, methodical buildup to tonight’s main event. The crew woke to Mission Control playing Passion Pit’s “Sleepyhead,” then completed a perigee raise burn to shape their orbit, and held their daily medical conference, reportedly all nominal. The table below tracks every milestone from preflight through the end of Mission Day 2.

Live Mission Update · Artemis II

Artemis II Mission Status: Launch Through Trans-Lunar Injection

Orion spacecraft Integrity and its four-person crew are in high-Earth orbit following a successful April 1 liftoff from Kennedy Space Center. All pre-TLI milestones have been completed nominally. The critical Trans-Lunar Injection burn is scheduled for approximately 8:00 p.m. EDT tonight, April 2.

Date / Time (EDT) Milestone Status
Pre-Launch
Mar. 2026 Flight Readiness Review (FRR) All systems cleared for launch; crew officially assigned to flight ✓ Complete
Apr. 1 · ~2:30 PM Crew Ingress & Suit Checks Wiseman, Glover, Koch & Hansen board Orion; helmets, gloves & harnesses secured ✓ Complete
Apr. 1 · ~6:25 PM Terminal Count & Ground Launch Sequencer Handoff Automated sequencer takes control; weather upgraded to 90% “Go” ✓ Complete
Mission Day 0 — Wednesday, April 1, 2026
Apr. 1 · 6:35 PM Liftoff — Launch Complex 39B SLS clears the tower; first crewed lunar mission since Apollo 17 in 1972 ✓ Complete
Apr. 1 · ~6:36 PM Maximum Dynamic Pressure (Max-Q) Peak aerodynamic stress on vehicle during ascent; nominal ✓ Complete
Apr. 1 · ~6:38 PM Solid Rocket Booster (SRB) Separation Both five-segment boosters jettisoned after burn-out ✓ Complete
Apr. 1 · ~6:43 PM Main Engine Cutoff (MECO) & Core Stage Separation RS-25 engines shut down; core stage separated — end of first major propulsion phase ✓ Complete
Apr. 1 · ~6:53 PM Solar Array Wing (SAW) Deployment All four ~23-foot solar wings unfurled; Orion on continuous electrical power ✓ Complete
Apr. 1 · ~7:24 PM ICPS Perigee Raise Maneuver (T+49 min) ICPS raises orbit’s low point; ensures crew can safely return to Earth if needed ✓ Complete
Apr. 1 · ~8:23 PM ICPS Apogee Raise Maneuver (T+1:48) ICPS raises orbit to ~1,500 × 46,000 miles; transitions to Deep Space Network comms ✓ Complete
Apr. 1 · ~9:59 PM Orion / ICPS Separation (T+3:24) Pilot Glover takes manual control; Orion flies free for the first time ✓ Complete
Apr. 1 · ~10:00 PM Proximity Operations Demonstration (~70 min) Glover manually pilots Orion around the ICPS; propulsion & proximity systems verified ✓ Complete
Apr. 1 · Late Night CubeSat Ejection & ICPS Deorbit Four international CubeSats released; ICPS performs deorbit burn for atmospheric reentry ✓ Complete
Apr. 1 · Late Night Crew Rest Period — Day 0 Sleep Shift Crew stores launch suits, stows for sleep; first rest period before Day 1 burns ✓ Complete
Mission Day 1 — Thursday, April 2, 2026
Apr. 2 · Early AM Crew Wakeup Mission Control played “Sleepyhead” by Young & Sick to wake the crew ✓ Complete
Apr. 2 · Morning Orion Perigee Raise Burn (~1 min) Orion’s ESM engine adjusts orbital path; final pre-TLI orbit shaping maneuver ✓ Complete
Apr. 2 · Midday Daily Medical Conference Crew reports health status and any concerns to flight surgeons in Houston ✓ Complete
Apr. 2 · ~8:00 PM Trans-Lunar Injection (TLI) Burn Orion’s AJ10 ESM engine fires; velocity increases to ~24,500 mph, escaping Earth orbit — the “rocket punch” to the Moon ▶ Upcoming
Apr. 2 · After TLI Emergency Communication System Test Crew tests backup comms equipment shortly after TLI, then returns to sleep — Planned
Apr. 2 · After TLI Outbound Lunar Coast Begins Integrity departs Earth orbit on a free-return trajectory; ~4-day coast to the Moon — Planned
Mission Day 2 — Friday, April 3, 2026
Apr. 3 Crew Rest & Overnight Translunar Coast Orion continues outbound on free-return arc; lunar gravity not yet dominant — Planned
Apr. 3 Day 2 Systems Checks & Science Operations Crew conducts engineering checkouts, experiments, and daily medical conference — Planned
Apr. 3 Outbound Coast Continues — ~200,000 mi from Earth Orion gradually decelerates against Earth gravity; Moon’s pull not dominant until ~41,000 mi out — Planned

✓ Complete = confirmed nominal  |  ▶ Upcoming = imminent or in progress  |  — Planned = scheduled pending prior milestones  |  All times Eastern Daylight Time (EDT). Mission continues toward lunar flyby on approximately April 6 and splashdown in the Pacific Ocean on April 10, 2026. Sources: NASA. Last updated April 2, 2026.

“`

“Before TLI, we want to make sure the life support systems are functioning properly and that the vehicle is healthy. Once we commit to TLI, those systems must work,” said Knight.

That decision will come today, and if it is “Go” the TLI burn happen about one day into the mission, roughly around the same time as launch: about 6:35 PM Eastern Daylight Time. Stay tuned.

“After a brief 54-year intermission, NASA is back in the business of sending astronauts to the Moon,” — Jared Isaacman, April 1, 2026